Plinth Construction Work

1. Preliminaries

  • Site preparation – Clear area, establish site facilities.
  • Area identification & clearing – Demarcate footprint and clear vegetation/obstacles.
  • Survey setting out – Confirm levels and positioning as per drawings.
  • Fencing – Temporary site fencing for safety and demarcation.

2. Earthworks & Foundations

  • Excavation (TLB) – Excavate to required depth and dimensions.
  • Layer filling – Place selected fill material in layers.
  • Compacting – Compact each layer to required density.
  • MOD testing – Laboratory/field density tests for compaction approval.
  • Repeat layer filling, compaction, and MOD testing until required foundation level is achieved.

3. Structural Works

  • Steel works delivery – Rebar and reinforcement delivered to site.
  • Steel works placement – Fix reinforcement as per drawings/specifications.
  • Engineer sign-off – Structural engineer inspection and approval.
  • Concrete placement – Pour concrete for plinth.
  • Shuttering (if required) – Install and remove formwork as per sequence.

4. Backfilling & Finishing

  • Backfill – Place and compact around completed plinth.
  • Finishing – Trowel, cure, and protect concrete surfaces.
  • Cleanup – Remove waste, excess material, and temporary works.
  • Handover – Final inspection, sign-off, and client acceptance.